To edit the project calendars, choose
ProjectManage Calendars.
Project Calendars assist us in scheduling by defining when resources can be
used in terms of working and nonworking days, and the hours they are
available on working days.  On the left is the name of the calendar being
displayed, in the center is the calendar, and on the right hand side are the
ranges of working hours for the selected day.  The default calendar shown below
depicts a typical
working month, with weekends grayed out, signifying that they are nonworking days.
In the Gantt chart, nonworking days are also grayed out.  Any changes
made to the project default calendar will be reflected in the Gantt Chart.
To make changes to a calendar, select the day to be changed, and then one of the
3 available radio buttons:
Use working time from derived calendar - uses the
parent calendar to determine the working time for that day.  See
for more information.
Set day type to: - uses the selected day type to
determine the working hours for that day.  See the section on
for more information.
Custom working time - defines a unique set of
working hours for a specific day.