To edit resource properties that are not displayed in the resource
view, right click on the resource and choose Edit
resource.
The General tab shows the same items that are in the resource view.
The Calendar tab allows us to assign a calendar to a specific resource	  if the project default calendar is not appropriate.  See
for more information on setting the
project default calendar.
To change the calendar assigned to a resource, simply select it from
the list. If you would like to create a new calendar for this
resource, you can do so from this dialog by clicking the
Edit calendars button.  See
the section  for more information.
Any tasks assigned to a resource with a specific calendar will use
the calendar assigned to the resource to schedule the work to be done.	  Therefore, if a task appears to be scheduled for a longer than
expected time period, it is likely that the resource is using a
calendar that is different from the project default.